e|agenda.NET Sarasota County Schools |
THE SCHOOL BOARD OF SARASOTA COUNTY, FLORIDA Landings Administrative Complex 1980 Landings Blvd. 3:00 P. M. |
Agenda Item #33 Title ACCEPTANCE OF SUBSTANTIAL COMPLETION FOR THE BROOKSIDE MIDDLE SCHOOL - CTE LABS CONSTRUCTION PROJECT Description The architect has prepared the Certificate of Substantial Completion and the final punch list. The project is substantially complete in accordance with the contract documents. A copy of the final punch list is available for review at the Construction Services Department. Recommendation That work performed by Magnum Builders of Sarasota for the Brookside Middle School - CTE Labs Construction project be accepted as substantially complete as of 8/11/2008. Contact LEMPE & COLLINS Financial Impact N/A Attachment: BAIenc9-16-08BrksideMS-CTE-ConstSC.pdf |